Gushing in from all corners, all sides, the country's most massive
concrete pour ever streamed into Calgary's

Bow
tower site downtown Saturday, marking the start of construction for
what will be the tallest building in Western Canada.
More than 68 trucks delivering enough concrete for 2,800 home
foundations made their way through downtown streets starting Friday
and continuing into this afternoon as part of the first stage of the
new headquarters for Encana Corp.
The 36-hour continuous run of concrete, involving more than 500
workers, shatters previous Calgary records, including pours for the
Calgary Tower and Stampede Corral.
"There has never been a base of a building (in Canada) that's
actually this big and this deep," said Michael Brown, associate
vice-president for Matthews Development, builder for the project.
Not only is it the largest pour to happen on Canadian soil, but it
is the third largest in the world, behind the Howard Hughes Center
in Los Angeles and the Al Durrah Tower in Dubai.
To fill the 2,787 square metre base more than 1,000 truckloads of
concrete were used, pouring more than 14,000 cubic metres of
concrete into the six storey hole. Although it is expected to dry in
a few days, crews will stay off for a couple of weeks "just to be
safe," said Brown.
A huge amount of concrete is needed to ensure a solid base for the
building, said Brown.
Because
the building is very tall and very large, many things were
considered in the three months it took to plan the pour, including
the consistency of the ground under the foundation.
As well, planners had to figure out the best way to bring the
concrete into downtown, including co-ordinating timing of the trucks
so the concrete remained at a proper consistency and workers could
manage continuous pouring.
Once the foundation has dried, steel columns will be erected,
forming the skeleton of the 58-storey building. From there,
construction of a six-storey underground parkade will begin.
The first floor of the building is expected to be built by the
beginning of October, and from there crews will build one floor per
week. The exterior construction is expected to take until fall 2009,
and Brown says the entire project will be finished sometime in
2011.
"When you build a building of this magnitude you have a number of
milestones. Today is probably one of the bigger milestones we are
going to achieve this year," said Brown.
With a price tag of over $10 million, this weekend's pour is small
portion of the $1 billion needed for the exterior construction. An
additional $1.5 billion will go inside the building in the form of
mechanics and furnishings.
"This is a very important building for downtown Calgary," said mayor
Dave Bronconnier, who was at the site Saturday morning.
"It's a huge part of our heritage and history."
And despite speculation the construction will interfere with this
year's Stampede parade, Bronconnier said 6th Avenue will reopen by
early July and "the parade will go as scheduled without question."
Since the closure of 6th Avenue last August, to make way for
excavation of the tower, commuters have run into traffic jams
downtown. And while the city can't promise that roads won't need to
be closed as the tower is built, they will make sure to let people
know early and often said Colleen Brown, communications advisor for
traffic engineering for the City of Calgary.
"We don't necessarily know what closures will happen," she said.
"For now we are recommending that people avoid the area as much as
they can."
As far as noise, Calgarians won't have to deal with the extreme
levels caused by the pour, but can expect the regular sounds that
would come from any construction site, said Kerry Gillis, senior
vice president of operations for Ledcor Construction, the
construction manager for the project.
"Unfortunately there's not much we can do about the noise," he said.
Kerry said the unique shape of the tower will help minimize its
environmental footprint. Lots of windows will
ensure
maximum daylight and environmentally friendly electrical and
mechanical fixtures will be installed.
"If you have those green attributes it saves you money in your
operating costs," he said.
The tower is sure to be a sight once completed, said Michael Brown.
The square-footage of the building, makes it 30 to 60 percent bigger
than most other buildings in downtown Calgary.
"It's going to redefine the Calgary skyline," he
said.